- Central Asia Regional Hub (Bishkek, Kyrgyzstan)
- Henan Kaifeng Dakang 16.8m Mobile Tunnel Kiln
- High-Efficiency Brick Manufacturing (Yulin, Shaanxi)
- The Andijan High-Efficiency Giant (Uzbekistan)
- The Harare Resilience Project (Zimbabwe)
- The Hoang Quy Modernization Project (Vietnam)
- The Jakarta Efficiency Project (Indonesia)
- The Quang Binh Energy Recovery Site (Vietnam)
- The Samarkand Industrial Landmark (Uzbekistan)
- The Tashkent Infrastructure Benchmark (Uzbekistan)
- The Vientiane National Project (Laos)
The Vientiane National Project (Laos)
The Vientiane National Project (Laos)
Country: Uzbekistan
Location: Samarkand
Daily Capacity: 400,000 – 500,000 Standard Bricks
Kiln Cross-Section: 12.98Meters
Kiln Diameter: 170 Meters

Case Introduction
Core Focus: EPC Solution for New Industrial Entrants
1. Project Background
The Laos market is in its early stages of industrialization. Our client was an investor entering the brick industry for the first time, requiring a "Turnkey" (EPC) solution where we handled everything from design to staff training.
2. Technical Specs
11.8-meter section and 138-meter diameter.
User-Friendly Automation: Since local operators were new to kiln technology, we installed a simplified, icon-based HMI (Human-Machine Interface) in the control room, allowing for easy monitoring.
Voltage Stabilization: To counter local power grid fluctuations, we included a comprehensive industrial voltage stabilization system to protect the motors and PLC.
3. Result
300,000 to 400,000 bricks per day. This is now the most advanced brick plant in Laos, serving as a model for future industrial development.




CONTACT US